City-wide Paving Projects

Post Date:03/15/2017 12:07 PM

The City of Williamsburg began its annual paving program on Thursday, March 16, 2017. It consists of milling, paving and striping streets in several areas across the City. Work is being coordinated around special events and schedules such as W&M graduation (May 13). Where appropriate, “No Parking” signs will be posted in the affected areas one day prior to the beginning of work.

Motorists should be prepared for the following:

  • Changing traffic patterns.
  • A reduction in speed in the work area.
  • Uneven and rough pavement at times.
  • Unmarked (no stripes) pavement at times.
  • All residences and businesses in the paving area will be accessible except for a brief time when the asphalt is initially placed and compacted.

In total, the 2017 paving program will cost an estimated $715,777.00, 57% of which is paid from State of Good Repair Funds (VDOT) and 43% by the City of Williamsburg. The entire paving program is expected to be completed by July 1. For more information, please call the Public Works Department at (757) 220-6140.

 

Please note that schedules are subject to change due to weather conditions.

 This schedule will be updated as dates are set with the contractor.

 Henry Street
 (not before May 14th)
 from Lafayette St. to Francis St.  Begin June 1

 Nassau Street
 (not before May 14th)

 from Prince George St. to Francis St.  Begin week of  June 5
 S. Boundary Street
 (not before May 14th)
 from Francis St. to South Henry St.  Begin week of  June 5
 Ireland Street
 (not before May 14th)
 from South Boundary St. to South Henry St.  Begin week of  June 5
 South England Street
 (not before May 14th)
 from Newport Ave. to end of city maintenance  & at entrance to Williamsburg Lodge  Begin week of  June 5
 Parkway Drive
 (not before May 14th)
 from Zelcolva Dr. to Second St.   Begin week of  June 12

 Bypass Road

from City Line to the east of intersection with SR 132 to Capitol Landing Rd. intersection

Completed

 Page Street

from Bypass Rd. to bridge over CSX railway, including section from bridge to tri-corner intersection

Completed

 Lafayette Street

from intersection of Francis, York & Lafayette streets to bridge over Colonial Parkway

Completed

 Haynes Drive

from Parkway Dr. to end of cul-de-sac

Completed

 Powhatan Street

from York St. to Beauregard St.

 Completed

 Pocahontas Street

from York St. to Pocahontas St. to Early St.

 Completed

 Beauregard Street

from Powhatan St. to Pocahontas St.

 Completed

 Tri-corner intersection

signalized intersection where Page, York, Francis & Lafayette streets intersect

 Completed

 Holly Hills Drive

from Sir Thomas Lunsford Dr. to cul-de-sac

 Completed

 Sir Lunsford Drive

from Holly Hills Dr. to cul-de-sac

 Completed

 Parke Court

from Sir Lunsford Dr. to cul-de-sac

 Completed

 Curls Neck Court

from Sir Lunsford Dr. to cul-de-sac

 Completed

 Pipe Kiln Court

from Sir Lunsford Dr. to cul-de-sac

 Completed

 Weston Court

from Sir Lunsford Dr. to cul-de-sac

 Completed

 Helmsley Drive

from Sir Lunsford Dr. to Yorkshire Dr.

 Completed

 Community Building access  road (not before May 14th)

from North Boundary St. to North Boundary St.
this includes all roads around the Community Building, the parking lot - the upper deck of the parking terrace will also be closed

 Deferred until  2018 due to  weather and  building use

 Jamestown Road

from Rt. 199 to South Boundary Rd.

 Completed

 

from Lafayette St. to Francis St.

from Lafayette St. to Francis St.

from Lafayette St. to Francis St.

Return to full list >>