City-wide Paving Projects

Post Date:03/15/2017 12:07 PM

The City of Williamsburg will begin its annual paving program on Thursday, March 16, 2017. This consists of milling, paving and striping streets in several areas across the City. Work is being coordinated around special events and schedules such as W&M graduation. Where appropriate, “No Parking” signs will be posted in the affected areas one day prior to the beginning of work.

Motorists should be prepared for the following:

  • Changing traffic patterns.
  • A reduction in speed in the work area.
  • Uneven and rough pavement at times.
  • Unmarked (no stripes) pavement at times.
  • All residences and businesses in the paving area will be accessible except for a brief time when the asphalt is initially placed and compacted.

In total, the 2017 paving program will cost an estimated $715,777.00, 57% of which is paid from State of Good Repair Funds (VDOT) and 43% by the City of Williamsburg. The entire paving program is expected to be completed by July 1. For more information, please call the Public Works Department at (757) 220-6140.

 

Please note that schedules are subject to change due to weather conditions.

 This schedule will be updated as dates are set with the contractor.

Bypass Road

from City Line to the east of intersection with SR 132 to Capitol Landing Rd. intersection

Completed

Page Street

from Bypass Rd. to bridge over CSX railway, including section from bridge to tri-corner intersection

Completed

Lafayette Street

from intersection of Francis, York & Lafayette streets to bridge over Colonial Parkway

Begin March 23

Haynes Drive

from Parkway Dr. to end of cul-de-sac

Completed

Powhatan Street

from York St. to Beauregard St.

Begin March 22

Pocahantas Street

from York St. to Pocahantas St. to Early St.

Begin March 22

Beauregard Street

from Powhatan St. to Pocahantas St.

Begin March 22

Tri-corner intersection

signalized intersection where Page, York, Francis & Lafayette streets intersect

Begin March 28

Holly Hills Drive

from Sir Thomas Lunsford Dr. to cul-de-sac

Begin March 29

Sir Lunsford Drive

from Holly Hills Dr. to cul-de-sac

Begin March 29

Parke Court

from Sir Lunsford Dr. to cul-de-sac

Begin March 29

Curtis Neck Court

from Sir Lunsford Dr. to cul-de-sac

Begin March 29

Pipe Kiln Court

from Sir Lunsford Dr. to cul-de-sac

Begin March 29

Weston Court

from Sir Lunsford Dr. to cul-de-sac

Begin March 29

Helmsley Drive

from Sir Lunsford Dr. to Yorkshire Dr.

Begin March 29

Henry Street
(not before May 14th)

from Lafayette St. to Francis St.

 

Nassau Street
(not before May 14th)

from Prince George St. to Francis St.

 

South Boundary Street
(not before May 14th)

from Francis St. to South Henry St.

 

Ireland Street
(not before May 14th)

from South Boundary St. to South Henry St.

 

Community Building access road (not before May 14th)

from North Boundary St. to North Boundary St.

 

South England Street
(not before May 14th)

from Newport Ave. to end of city maintenance & at entrance to Williamsburg Lodge

Parkway Drive

from Zelkova Dr. to Second St.

 

Jamestown Road
(not during May 7th-14th)

from Rt. 199 to South Boundary Rd.

Restriping only