CITY OF WILLIAMSBURG
SALES TAX FUND
CAPITAL IMPROVEMENTS PLAN
FISCAL YEARS 2004-2008
                 
(Click for a printer-friendly PDF version)
                 
                 
               
CATEGORY BUDGET FOR PLANNING PURPOSES ONLY  
Project Title FY: 2003 2004 2005 2006 2007 2008 TOTAL
    carry over            
                 
PUBLIC WORKS              
Street Construction (Note 1)              
  Richmond Road - Brooks St to New Hope 71,600   50,000 50,000     171,600
  Treyburn Extension (VDOT) 200,000 1,040,000 4,900,000 925,000     7,065,000
  Ironbound / Monticello (VDOT)   10,000         10,000
  Jamestown Road Improvements             0
  Prince George / Boundary St. Streetscape   880,000         880,000
                 
Underground Wiring/Beautification              
  Richmond Road - Brooks to New Hope   Note 2          
  Monticello Ave - Richmond Rd to Mt.Vernon 100,000 400,000         500,000
  Lafayette Street (East End)     200,000       200,000
  S. Henry Street         500,000 400,000 900,000
  Underground Wiring Assessment Program              
                 
Pedestrian and Bicycle Improvements              
  Sidewalk Construction Plan   100,000 50,000 70,000 50,000 125,000 395,000
                 
Stormwater Management              
  Stormwater Management Projects   125,000 150,000 140,000 55,000 100,000 570,000
                 
  Total Public Works 371,600 2,555,000 5,350,000 1,185,000 605,000 625,000 10,691,600
                 
                 
                 
                 
RECREATION AND OPEN SPACE              
  Quarterpath Park Improvements              
  Reroof Gym   78,000         78,000
  Resurface Tennis Courts     30,000       30,000
  Interior Gym Walls       65,000     65,000
  Rehab Gym Floor         25,000   25,000
                 
  Waller Mill Park Improvements              
  Site Improvements on Point     175,000       175,000
                 
  Kiwanis Park Improvements              
  Replace Fences   30,000         30,000
  Upgrade Press Boxes     65,000       65,000
  Resurface Tennis Courts       40,000     40,000
  Replace Lighting         100,000   100,000
  Replace Maintenance Building           140,000 140,000
                 
  Park Development Planning              
  Papermill Park     25,000       25,000
  Capitol Landing Park       25,000     25,000
                 
  Total Recreation and Open Space 0 108,000 295,000 130,000 125,000 140,000 798,000
                 
                 
                 
                 
GENERAL GOVERNMENT              
Public Facilities              
  Prince George Parking Garage (see Note 3) 3,540,000           3,540,000
  Fire Station Rehabilitation   145,000 25,000 85,000 30,000   285,000
  Vehicle Wash and Oil Capture System     50,000       50,000
  Salt Storage Facility   10,000 130,000       140,000
                 
Vehicles and Equipment              
  Vehicle Replacement Plan   234,000 438,000 492,000 218,000 155,000 1,537,000
  Police Communications       150,000 120,000   270,000
                 
Property Purchase              
  High Street Properties   159,996 159,996 159,996 159,996 1,459,996 2,099,980
                 
Contingency              
  Capital Projects Fund Contingency   200,000 1,000,000 1,000,000 1,000,000 1,000,000 4,200,000
                 
Agencies / Interjurisdictional              
  Regional Library Renovations   18,500 52,800       71,300
  Strawberry Plains Redevelopment Area 160,000