Paving Schedule

The City of Williamsburg will begin its annual paving program the week of May 23, 2022 . This consists of milling and paving streets, or street segments, in several areas across the City. “No Parking” signs will be posted in the affected areas one day prior to the beginning of work. 

This page will be updated as information is received by the contractor. It is important to note that the schedule is subject to change due to weather conditions.

Motorists should be prepared for the following:

  • Changing traffic patterns – expect single lane closures during road work.
  • A reduction in speed in the work area.
  • Uneven and rough pavement at times.
  • Unmarked pavement.
  • Residences and businesses in the paving area will be accessible except for a brief time when the asphalt is initially placed and compacted.


Paving Schedule 2022 

Please note that schedules are subject to change due to weather conditions. 

This schedule will be updated as dates are set with the contractor.

Street Limits Milling Paving
Jamestown Road Route 199 to Lake Matoaka Dam Week of May 23 Week of May 30

South Henry Street Francis Street to Route 199 June 2 Week of June 6
Quarterpath Recreation Center Parking Lot Ballfield to tennis courts Week of June 13 As early as June 16
Harrison Avenue Richmond Road - West to end of City right-of-way Week of June 21 As early as June 24
North Henry Street Route 132 to cul-de-sac Week of June 21 As early as June 24
Dunning Street Route 132 to end Week of June 21 As early as June 24
Burbank Street North Henry Street to end Week of June 21 As early as June 24
Roycroft Street North Henry Street to Henderson Street Week of June 21 As early as June 24
Henderson Street North Henry Street to Roycroft Street Week of June 21 As early as June 24
Alice Street Burbank Street to Roycroft Street Week of June 21 As early as June 24
Harrison Avenue Richmond Road - West to end of City right-of-way June 30 June 30